The short answer
What a construction delay expert does on a Pinellas County matter
Oxley provides construction delay expert witness services to counsel and parties in Pinellas County construction disputes. Daniel R. Zorrilla, J.D., BSBC, CGC, CFCC, leads the work as testifying expert. He examines the baseline, the schedule updates and the project records to determine whether completion was delayed, which events affected the critical path, and how much time each accounted for. How concurrent delay is treated depends on the contract and applicable law, which are for counsel and the tribunal.
The method is chosen to fit the contract and the records, stated in the report and explained in testimony at deposition, trial or arbitration, and presented at mediation. The analysis addresses the record, including evidence that cuts against the retaining party.
Oxley’s office is at 13830 58th St N, Suite 403, Clearwater, FL 33760, in the middle of Pinellas County. It is about 10 miles by road from the Clearwater Courthouse and about 12.5 miles from the St. Petersburg Judicial Building.
- Testifying expertDaniel R. Zorrilla, J.D., BSBC, CGC, CFCC, President
- Scheduling teamDavid Hengelbrok, P.E., PSP, and Jeremy Easen, BSBC, CGC
- TestimonyDan has testified in more than 40 cases, in state and federal court and in arbitration. He has been retained as a consultant or expert in more than 100 construction matters.
- Phone727-821-9190
Pinellas County projects
What delay looks like on Pinellas County projects
Pinellas is a built-out peninsula with 24 municipalities, so much of its construction is renovation and redevelopment. Older buildings are replaced or rebuilt, utilities are upgraded under existing streets, and waterfront properties are rebuilt after storms. There is little open land, so projects often sit on tight sites with neighbors, active streets and limited staging.
Renovation and redevelopment schedules carry risks that new construction on an open site does not. Existing conditions are discovered only as walls and ceilings open. Work in occupied buildings is phased around tenants, residents or operations, with restricted hours and access. Older utilities and structures add investigation and redesign. When the project runs long, the analysis has to separate time caused by those conditions from time caused by planning, staffing or procurement.
On these jobs, productivity often suffers before completion does. Lost efficiency from working around occupants, out-of-sequence work or trade stacking can be real even where the critical path held. Lost productivity and lost time are separate questions with separate proof.
Delay can also trace to contractor staffing, subcontractor performance, sequencing and rework. A fair analysis weighs those causes alongside owner-side causes and states which events the records support.
Coastal work adds its own questions. Hurricanes Helene and Milton in 2024 brought repair and rebuilding work to the county’s beach communities. Storm-driven projects raise questions about whether weather days were excusable, how long a repair should reasonably take, how permitting and material availability affected duration, and how insurance-funded scopes changed over time. Floodplain and coastal permitting requirements can also shape the scope and the sequence on waterfront properties.
Owners and contractors may be working under different contract forms, public or private, each with its own schedule specification, update cycle and extension procedure. A delay opinion starts with the specific contract on the specific project. It does not start with a general rule for the county.
Records
Records that matter most in a Pinellas County delay claim
Delay opinions rest on dated records. These are the records that usually matter most on this kind of project, and the earlier they are preserved, the more an analysis can support.
- Native schedule files for the baseline and every update, with the narratives that came with them
- Owner, architect and contractor (OAC) meeting minutes and three-week look-aheads
- Submittal and procurement logs, with approval and delivery dates
- Notices, time extension requests and change orders, with the owner’s responses and dates
- Surveys and investigations of the existing building, and what they did and did not cover
- RFIs, design responses and revised drawings issued after demolition opened the work
- Phasing plans, occupant notices and access restrictions in effect at each stage
- Permit and inspection histories, including any re-inspections
- Dated photographs and daily reports showing crew size and work areas
With those records the analysis can tie each period of delay to a documented event and to the dates in the record. How the contract allocates that time is for counsel and the tribunal.
For a subcontractor, the analysis also uses the general contractor’s updates as issued, the look-aheads and the subcontract’s schedule and notice terms.
Method
How the analysis method is chosen
Oxley chooses the analysis method to fit the contract and the records, including windows analysis, as-planned versus as-built comparison, time impact analysis and as-built reconstruction, as described in AACE International Recommended Practice No. 29R-03. The report names the method and explains why it fits. Method detail is on the construction delay expert witnesses page.
Courts and forums
Where Pinellas County delay disputes are heard
State court: Sixth Judicial Circuit (Pinellas and Pasco), at the Clearwater Courthouse, 315 Court St., and the St. Petersburg Judicial Building, 545 1st Ave. N.
Federal court: Middle District of Florida, Tampa Division, 801 N. Florida Ave., Tampa, which includes Pinellas County.
Appeals and arbitration: state appeals go to the Second District Court of Appeal, headquartered in St. Petersburg. Private contracts frequently call for AAA arbitration or another agreed procedure. Dan has testified in arbitration as well as in court.
In every forum the delay opinion has to rest on a stated method and on the project records. The analysis follows the governing contract and the forum’s rules on expert testimony.
Who does the work
Daniel R. Zorrilla, J.D., BSBC, CGC, CFCC
Dan Zorrilla is Oxley’s President and testifying expert on construction schedule delay, disruption, lost productivity, cumulative impact and related damages. He has been in construction since 1991 and in consulting and expert work since 2008. He managed construction for national and regional general contractors before 2008 and returned to project management in 2014–2015. He is a Florida Certified General Contractor, an AACE International Certified Forensic Claims Consultant, a Panelist of the American Arbitration Association, and a member of The Florida Bar. He does not practice law. Work through Oxley is technical consulting, not legal representation. Full profile →
David Hengelbrok, P.E., PSP, and Jeremy Easen, BSBC, CGC, support the scheduling and delay analysis.
Oxley acts for only one party on a project, and fees do not depend on findings. Any earlier role on the project is disclosed at intake.
When this comes up
Situations that call for a delay expert
- Completion delay and related cost consequences are disputed
- An owner needs to test a contractor’s time extension request or support a liquidated damages assessment
- An extension request or a liquidated damages assessment is contested
- An opposing expert’s delay analysis needs a response
- Counsel needs an early view of what the schedules actually support
- Schedule analysis is needed while the project is still running. See schedule review and analysis and delay analysis for contractors
Related work includes delay damages and disruption.
FAQ
Pinellas County construction delay expert witnesses: common questions
Does Oxley have an office in Pinellas County?
Yes. Oxley’s office is at 13830 58th St N, Suite 403, Clearwater, FL 33760, in Pinellas County.
What does a construction delay expert witness do?
A delay expert examines the schedules and records to determine whether completion was delayed, which events affected the critical path and how much time each accounted for. The expert states the method and its limits in a report and in testimony at deposition, trial or arbitration, and presents the analysis at mediation.
Who is the testifying expert?
Daniel R. Zorrilla, J.D., BSBC, CGC, CFCC, is Oxley’s President and testifying expert on schedule delay, disruption and related damages. David Hengelbrok, P.E., PSP, and Jeremy Easen, BSBC, CGC, support the scheduling and delay analysis. His CV and testimony history are available to counsel on request.
Which courts hear Pinellas County construction delay disputes?
State cases are heard in the Sixth Judicial Circuit, which covers Pinellas and Pasco counties, at the Clearwater Courthouse and the St. Petersburg Judicial Building. Federal cases are heard in the Middle District of Florida, Tampa Division. Many construction contracts send disputes to arbitration instead. Dan has testified in arbitration as well as in court.
When should an owner, contractor or counsel bring in a delay expert?
Often earlier than expected. An owner may need to test a contractor’s time extension request or support a liquidated damages assessment. A contractor may need to document delay while the records are current. Counsel may need a view when successive updates move the forecast completion date, before mediation, or when an opposing delay analysis needs a response. On renovation and storm repair work, an early limited look can also show whether the existing-condition and phasing records are complete enough to support an analysis.
Does Oxley act for both sides on the same project?
No. Oxley acts for only one party on a project, and fees do not depend on the findings. Any earlier role on the project is disclosed at intake. Oxley provides technical consulting, not legal representation.