Project Progress Monitoring

Progress monitoring may support an owner’s assessment of reported progress, forecasts and the available project records.

Owners, lenders and public bodies all rely on reported progress for decisions that are hard to unwind, payment, financing, occupancy planning, and the sequencing of work by others. When reported progress is optimistic, those decisions are made on a picture that does not exist.

Progress and payment information may be evaluated using measures suited to the contract and work. Physical quantities, reported percentages, milestones and other evidence have uses and limitations; differences are assessed in their contractual context.

Progress, production rates and forecasts may provide different information about a project. Trends, measurement changes and possible responses are considered in the circumstances rather than through a fixed hierarchy of indicators.

Contractor and owner records provide different views of the same work. Their usefulness rests on timing, support and consistency with the rest of the record. The author’s identity alone does not settle the weight of the information.

Partially completed building interior with visible mechanical and structural work

Possible assignment considerations

In practice

  1. 01

    Establish a technical baseline of fact

    Fix how progress will be measured and by whom, separately from the contractor's own reporting.

  2. 02

    Measure installed work

    Assess physical progress against the drawings and the schedule rather than accepting reported percentages.

  3. 03

    Reconcile against payment

    Compare observed and reported progress with the payment application using the contract's payment basis, including any stored materials or milestones.

  4. 04

    Report trend, not just status

    Track production rates period on period and flag divergence while the response options are still inexpensive.

Considerations and limitations

Questions and limitations to consider

Certifying on reported progress

Paying against percentages that were not checked against the work.

Watching the date instead of the rate

Monitoring the forecast finish while the underlying production trend goes unexamined.

Changing the method mid-job

Changing the measurement basis without evaluating its effect on comparability or explaining the adjustment.